Texas Foreclosure Timeline Calculator: Counting Your Dates by Hand
This page works as a calculator on paper. Given the date on a Texas notice of default or notice of sale, it shows how to count the minimum dates under Texas Property Code §51.002, so you can see the earliest point a sale could happen. Servicers often move more slowly than the minimum, but planning on the minimum gives you a margin.
The inputs
- Date the notice of default was sent (if you have one)
- Date the notice of sale was given (posted, filed and mailed)
- The sale date stated on the notice
The rules used
- A notice of default for a residence must give at least 20 days to cure.
- The notice of sale must be given at least 21 days before the sale.
- The sale is held on the first Tuesday of a month, between 10 a.m. and 4 p.m.
- Federal servicing rules generally require the borrower to be more than 120 days delinquent before the first foreclosure notice or filing.
Method
Step A: earliest end of the cure period. Add 20 days to the date the notice of default was sent. Before that date, the notice of sale should not have been possible on the minimum timeline.
Step B: earliest possible sale date after a notice of sale. Add 21 days to the date the notice of sale was given. Then find the first Tuesday of a month that falls on or after that date.
Step C: check the stated date. Compare the sale date on the notice with your Step B result. If the stated date is earlier than the earliest possible date you calculated, that is a question to raise promptly with an attorney.
A worked hypothetical
| Input | Hypothetical value |
|---|---|
| Notice of default sent | The 3rd of a month |
| Cure period ends (Step A) | 20 days later, the 23rd |
| Notice of sale given | The 25th of the same month |
| 21 days later (Step B) | The 15th of the next month |
| First Tuesday on or after that | The first Tuesday of the month after that |
In this made-up example, the earliest first-Tuesday sale is almost two months after the notice of default. If the next month's first Tuesday had fallen on or after the 15th, it would have been the earliest date instead.
Your planner
| Item | Your date |
|---|---|
| Notice of default sent | |
| Plus 20 days | |
| Notice of sale given | |
| Plus 21 days | |
| Next first Tuesday on or after that | |
| Sale date on the notice | |
| Days from today to the sale date |
What the result tells you
The number of days left is your planning window. Reinstatement, a loss-mitigation review, a sale and closing, or legal advice all have to fit inside it. With fewer than about three weeks, a sale is hard to close unless a postponement is agreed in writing.
Limits
This method covers the statutory minimums only. It does not check whether notices were properly delivered or whether federal protections apply. Home equity loans, reverse mortgages, many HOA liens and tax liens follow different processes.
WholeSellIn TX offers this method for general education. A HUD-approved housing counselor can check your dates with you for free, and a Texas attorney can review any notice you think is defective.